Design stalled while Phase 1 utility work wrapped up; council approved $216,610 to resume design and directed the $200,000 state grant there. Some members want to revisit the 10-foot sidewalks and median islands to cut right-of-way costs.
At a glance
- Total mentions
- 1
- Last 30 days
- 1
Discussed at 1 meeting in the last 60 days; most recently Oct 13, 2026.
Impact analysis
$216,610 new design cost; roughly $100,000 of it is schedule-driven; county will reimburse $87,000 for water main design.
Pedestrians and drivers along Indian Trail Road get safer, wider sidewalks and a redesigned corridor.
None identified, though design changes could add costs.