Summary
The town awarded a $977,900 contract to Litman Excavation & Construction to build the park's new access road, with Shady Bluff Road expected to close after the park's phase three design next year.
At a glance
- Total mentions
- 1
- Last 30 days
- 0
Discussed at 1 meeting in the last 60 days; most recently Sep 8, 2026.
Impact analysis
$977,900 contract plus a budget amendment covering roughly $100,000 in contingency.
Park visitors gaining safer, dedicated access to Chestnut Square Park.
Shady Bluff Road users will see that road close once park phase three begins next year.