O
Indian Trail
← All issues
parks recMedium priorityopen

Chestnut Square Park access road construction

Indian Trail

Summary

The town awarded a $977,900 contract to Litman Excavation & Construction to build the park's new access road, with Shady Bluff Road expected to close after the park's phase three design next year.

At a glance

Total mentions
1
Last 30 days
0

Discussed at 1 meeting in the last 60 days; most recently Sep 8, 2026.

Impact analysis

💰Financial impact

$977,900 contract plus a budget amendment covering roughly $100,000 in contingency.

✅Who benefits

Park visitors gaining safer, dedicated access to Chestnut Square Park.

⚠️Who could be affected

Shady Bluff Road users will see that road close once park phase three begins next year.

Mentions & discussions (1)

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Indian Trail

What the council decided, in plain English — one email a week.

Also follow nearby cities

Free. Unsubscribe with one click any time. We never sell your email.